1 male/female tape.
viii) 25K/order; but not placed by Lacie. Order will come from their
accessories’ supplier!
l Electronic Projects:
1) D2 NAS Kirkwood: Target price US34! Need to kick off next week to the right vendor that can match this price... But Qi seems taking this exactly same BOM cost as per the original D2 NAS, and no wireless concern for now! Just don't understand how can people quote US13 on that PCBA. But need to feedback to Qi next week our reply! I have already provide the ME cost from our competitor to Joe. Also, rely on Rick to see how we can get exactly cost on PCBA. Than, quote our best to Qi next week. Dead line for Lacie to
kick off this project is before Feb 19th.
2) D2 Next Quadra 936, volume is very small. Qi said Lacie will just leave to Mapower. Therefore, spend less effort on it.
3) D2 Next: Target price US27! I have sent email to Joe to see if we can try
to match. Olivia, please follow up with Joe & confirm back to Qi before Feb
20th. 30K pending order ASAP, and potential 10-20K/month follow on, that
means 120 - 240K/year.
Power adapter: Lacie does not want to work with Sinfone and from now on, can be someone else, and 亚源! This vendor quo
te US3.65 to Lacie. This is the price JEM can use on
BOM. Actually all our competitor Maya, Mapower & Good man are using this price. Already told Joe that we are buying too expensive.
Sandy, Olivia & Jonathan will need to keep close contact with Joe, and make sure we confirm back to Qi next week our final offer on D2 Next & D2 NAS Kirkwood!
4) 1) 4 Big DAS: Already confirmed the project to JEM! Target T1 date is April 10, according to Samuel, but we have been waiting for the AD#. Samuel does not like us to keep pushing him on the AD#. Therefore, I have already informed him that if he delays to provide us the AD#, our schedule will postpone accordingly! JEM needs to make sure all ME issues are cleared with Samuel. According to Samuel, he has already explained clearly all information to Jason and Jason should understand all already! If not, please make sure to call Samuel fo
r a meeting to clear out the pending issues. JEM has to make all well prepared, & so, once AD# is received, we should just start without delay! This project is the #1 urgent project for Lacie now, because their GM also come out to ask for this schedule during the meeting. Samuel also want to remind JEM that their existing supplier has lots of defect on the cosmetic on that big enclosure! He hopes JEM can try to avoid all these problems! For detailed information about what quality problem their existing supplier is facing, he suggests us t